Project List for Stimulus Funding Applications
Funded Projects
| |
Project |
Cost $ |
Description |
Application
PDF |
| 1 |
Washmill Lake/102 Underpass/Regency Park |
10,000,000 |
Create a third entrance to Bayers Lake Business Park |
 |
| 2 |
Burnside/North Dartmouth (Trunk Sewer) |
4,000,000 |
Trunk Sewer will allow the expansion of Burnside Industrial Park in support of the Atlantic Gateway initiative |
 |
| 3 |
Sheet Harbour Sidewalks |
3,500,000 |
2.7 km of sidewalk and stormsewers |
 |
| 4 |
Waste Stabilization Facility Roof |
3,000,000 |
New roof for high rate composting facility at Otter Lake Landfill |
 |
| 5 |
Herring Cove Fire Station |
3,000,000 |
Replace an aging Fire Station in Herring Cove |
 |
| 6 |
Hubley Fire Station |
3,000,000 |
Replace an aging Fire Station in Hubley |
 |
| 7 |
Point Pleasant Park Upgrades |
2,000,000 |
Recapitalization projects including a major overhaul of roads/paths, shoreline stabilization, parking lots, gates and entrances. |
 |
| 8 |
Halifax City Hall Restoration |
2,000,000 |
Restoration of City Hall |
 |
| 9 |
Ernst Mill Bridge Replacement |
1,500,000 |
Replacement of Ernst Mill Bridge (Lake Major Road |
 |
| 10 |
Chester Spur Line |
1,000,000 |
Paved active transportation trail 8.6km long |
 |
| 11 |
All Buildings Bundle |
610,000 |
Boiler, window, plumbing, septic and elevator upgrades at Captain William Spry Centre, and the former Dartmouth City Hall. |
 |
Previously Submitted Projects - No Federal Stimulus Funding Received
| |
Project |
Cost $ |
Description |
Application
PDF |
Additional
Details PDF |
| 1 |
4-Pad Arena |
35,400,000 |
145,000 sq. ft. Quad Pad Arena Complex |
 |
|
| 2 |
Resurfacing |
12,391,000 |
Planing and patching covered by a thin overlay of asphalt. |
 |
 |
| 3 |
Burnside Phase12-3 |
5,500,000 |
Expand Burnside Business Park |
 |
|
| 4 |
Paving Renewal |
4,680,000 |
Renewal of damaged portions of road |
 |
 |
| 5 |
Pockwock Water Main |
4,000,000 |
Replace an aging water main (on behalf of Halifax Water) |
 |
|
| 6 |
Sidewalk & Curb Renewal |
2.909,400 |
Renewal of concrete sidewalk in need of replacement |
 |
 |
| 7 |
New Sidewalks |
2,660,000 |
New concrete sidewalks |
 |
 |
| 8 |
Crane Hill Rd. Bridge |
1,500,000 |
Replace Bridge near the end of it's service life. |
 |
|
| 9 |
Paving New Streets |
1,500,000 |
Paving HRM owned gravel subdivision streets |
 |
 |
| 10 |
Rehab Main Arteries |
1,500,000 |
Repair and replace damaged sections of road to help prevent water pooling and related damage. |
 |
 |
| 11 |
Main Street Widening |
1,248,000 |
Widening of Main Street to improve intersections, add bike lanes and renew sidewalks. |
 |
|
| 12 |
Intersection Improvements |
1,200,000 |
Includes intersections improvements needed in conjunction with the Hammonds Plains Road widening and the Novalea/Devonshire/Duffus conversion to a roundabout. |
 |
|
| 13 |
Active Transportation Trails |
500,000 |
Expand existing active transportation network |
 |
|
| 14 |
Park Pathways |
125,000 |
Recapitalization of existing pathways |
 |
|
Economic Impacts of Various HRM Infrastructure Projects - Information Report
|
|
|