2003 CAPITAL WORKS PROJECTS
updated as of March 3, 2004.

    TYPE OF REGION   START   COMPLETION   PERCENT
LOCATION LIMITS CONSTRUCTION AREA NO. PROP ACT PROP ACT COMPLETE
                   
AEROTECH DRIVE PRATT & WHITNEY TO HWY 102 2nd lift of asphalt CENTRAL 2 24-Jul-03 28-Jul-03 04-Sep-03 17-Oct-03 99%
AGRICOLA STREET DUFFUS TO SEBASTIAN, W sidewalk renewal WEST 11 02-Sep-03   01-Oct-03    
ALBERT STREET RECTOR TO VESTRY, W sidewalk renewal WEST 11 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
Allan Street Harvard to Chebucto watermain cleaning & lining WEST 14          
ALMON STREET OXFORD TO DUBLIN pavement resurfacing WEST 14 30-May-02 30-May-02 11-Jul-02 12-July-02 100%
ALMON STREET CONNOLLY TO CONNAUGHT, S sidewalk renewal WEST 14 02-Sep-03   01-Oct-03    
ANDERSON ST PUMPING STATION ANDERSON ST PUMPING STATION sewer EAST 7         44%
ARMSHORE DRIVE Armshore Drive - Bridge Repair bridge repair WEST 17          
ARTILLERY PLACE DRESDEN TO QUEEN pavement renewal WEST 12         0%
ASHGROVE AVENUE ATWOOD TO ADDISON pavement resurfacing EAST 5 29-May-03 29-May-03 11-Jul-03 23-Jun-03 100%
ASHGROVE AVENUE ADDISON TO COLBY sewer lining EAST 5 01-Nov-02 01-Nov-02 01-Oct-03   95%
ASHGROVE AVENUE ADDISION TO ANCASTER sewer lining EAST 5 15-Sep-03 15-Sep-03 10-Oct-03   10%
ASHTREE COURT WESTMONT TO END new paving EAST 4   01-Jun-03   15-Jul-03 100%
BARRINGTON STREET AT DUFFUS street rehab WEST 11 SPRING 2004      
BAYERS ROAD JOSEPH HOWE TO DUTCH VILLAGE, S sidewalk renewal WEST 15 24-Jun-03   08-Aug-03 08-Aug-03 100%
BEAVERBANK,BARRETT ROAD SUBDIVISION PHASE IV C sanitary sewer CENTRAL 19 23-Jun-03 23-Jun-03 09-Nov-03   98%
BEAVERBANK,MAYFLOWER SUBDIVISION PHASE IV B sewer project CENTRAL 19 16-Jun-03 16-Jun-03 01-Dec-03   99%
BEAVERBANK ROAD MILLWOOD TO GLENDALE - TRUNK SEWER trunk sewer CENTRAL 19 23-Sep-02 16-Sep-02 16-Dec-02 15-Jul-03 100%
BELLESHIRE DRIVE CULVERT RENEWAL sewer project CENTRAL 20 30-Sep-02   28-Oct-02   100%
BELMONT ON THE ARM BEAUFORT TO END resurfacing WEST 13 20-Aug-03 18-Aug-03 15-Oct-03 14-Nov-03 98%
BELMONT ROAD ROBIE TO BELLEVUE paving renewal WEST 13 20-Aug-03 18-Aug-03 15-Oct-03 14-Nov-03 98%
BISSETT ROAD CIVIC 65 TO REHAB paving renewal EAST 5 18-Sep-03 22-Sep-03 31-Oct-03   100%
BISSETT ROAD CIVIC 65 TO PATRICK LN new sidewalk EAST 5 18-Sep-03 22-Sep-03 31-Oct-03   100%
BLOOMINGDALE TERRACE JUBILEE TO NORWOOD, E sidewalk renewal WEST 13 23-Jun-03 23-Jun-03 04-Aug-03 13-Aug-03 100%
BLOOMINGDALE TERRACE JUBILEE TO NORWOOD, W sidewalk renewal WEST 13 23-Jun-03   04-Aug-03 13-Aug-03 100%
BLUEFOREST LANE CIVIC 79 TO END new paving WEST 22 17-Jun-03 18-Jun-03 14-Jul-03 02-Jul-03 100%
BOW STREET MANOR DRIVE TO END new curb EAST 10 24-Jul-03 28-Jul-03 04-Sep-03 17-Oct-03 100%
BRIARWOOD COURT RIVERSIDE TO END paving & sewer renewal CENTRAL 19 SPRING 2004        
Brock St. Johnstone to end watermain cleaning & lining EAST 8          
BRUCE STREET PORTLAND/BRUCE/SETTLE ST. pumping station upgrade EAST 7 07-Jul-03 14-Jul-03 01-Aug-03 03-Oct-03 100%
BURNHOPE DRIVE MONTAGUE TO 38 BURNHOPE new paving EAST 4   01-Jun-03   15-Jul-03 100%
CATAMARAN ROAD SANITARY SEWER OLD SAMBRO TO HERRING COVE trunk sewer WEST 18 15-Sep-03 15-Sep-03 08-Nov-03   94%
CENTRE STREET PINE TO END storm sewer WEST 12 28-Aug-03 28-Aug-03 09-Oct-03   100%
Chebucto Rd., Hfx. Oxford to Windsor watermain cleaning & lining WEST 14          
CHISHOLM AVENUE MIC MAC TO McALPINE, S sidewalk renewal WEST 11 24-Jun-03   08-Aug-03 18-Aug-03 100%
CONNAUGHT AVENUE ROSLYN TO CHESTER pavement resurfacing WEST 11 30-May-02 30-May-02 11-Jul-02 13-Jul-02 100%
CONNAUGHT AVENUE CHISHOLM TO CHESTER, E pavement resurfacing WEST 11 26-May-03 26-May-03 7-Jul-03   100%
CONNAUGHT AVENUE CHISHOLM TO WINDSOR, E sidewalk renewal WEST 11 26-May-03 26-May-03 7-Jul-03   100%
CONNAUGHT AVENUE CHESTER TO CHISHOLM, E sidewalk renewal WEST 11 26-May-03 26-May-03 7-Jul-03   100%
CORK STREET CONNOLLY TO CONNAUGHT, N sidewalk renewal WEST 14 02-Sep-03 02-Sep-03 01-Oct-03 31-Oct-03 100%
CORONATION AVENUE BIRCH TO END paving renewal WEST 15   13-Oct-03     40%
CORONATION AVENUE WILLETT TO HILLCREST paving renewal WEST 15   13-Oct-03     40%
DEACON STREET ALMON TO END, W sidewalk renewal WEST 14 02-Sep-03 02-Sep-03 01-Oct-03 31-Oct-03 100%
DESMOND AVENUE BAYERS TO SCOTT culvert rehabilitation WEST 15 30-Jun-03 17-Jul-03 18-Aug-03   100%
DOROTHEA DRIVE REGAL TO SPRING paving renewal EAST 7 18-Sep-03 22-Sep-03 31-Oct-03   100%
DUBLIN STREET ALMON TO CORK paving renewal WEST 14 08-Oct-03 08-Oct-03 05-Dec-03   97%
DUMBARTON AVENUE CAIRNDOW TO KINCARDINE, N new sidewalk EAST 6 07-Aug-03 11-Aug-03 05-Oct-03   100%
DUMBARTON AVENUE CALEDONIA TO KINCARDINE paving renewal EAST 6 07-Aug-03 11-Aug-03 05-Oct-03   100%
Duncan St., Hfx. Chebucto Ln to Windsor watermain cleaning & lining WEST 14          
Dustan St., Dart. Rodney to Fenwick watermain cleaning & lining EAST 8          
EASTWOOD COURT ARKLOW TO END pavement resurfacing EAST 4 29-May-03 29-May-03 11-Jul-03 23-Jun-03 100%
EDGEWOOD AVENUE BERESFORD TO CONNOLLY, S sidewalk renewal WEST 11 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
EDWARD LAURIE DRIVE WEDGEWOOD TO ROBERT ALLEN paving renewal WEST 16 20-Aug-03 20-Aug-03 15-Oct-03 15-Oct-03 100%
ELMWOOD AVENUE HESTER TO WINDMILL, N sidewalk renewal EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ELMWOOD AVENUE HESTER TO WINDMILL pavement resurfacing EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ELMWOOD AVENUE HESTER TO WINDMILL, S sidewalk renewal EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ELMWOOD AVENUE WYSE TO BEDFORD, W new sidewalk EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ELMWOOD AVENUE WYSE TO BEDFORD pavement resurfacing EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ELMWOOD AVENUE BEDFORD TO WYSE, S sidewalk renewal EAST 9 11-Jun-03 11-Jun-03 18-Jul-03 31-Jul-03 100%
ESDAILE AVENUE TUPPER TO BOUNDARY paving renewal EAST 8 07-Aug-03   05-Oct-03   100%
FALL RIVER ROAD TRUNK 2 TO BLUEHILL pavement resurfacing CENTRAL 2   16-Aug-03     99%
FENWICK STREET SOUTH PARK TO QUEEN paving renewal WEST 13 08-Oct-03 08-Oct-03 05-Dec-03    
FENWICK STREET AT QUEEN STREET sewer lining WEST 13 15-Sep-03 15-Sep-03 10-Oct-03 15-Dec-03; 100%
FENWOOD ROAD ST.MARGARETS TO STONEHAVEN paving renewal WEST 17 18-Aug-03 19-Aug-03 10-Oct-03   85%
FERGUSONS COVE RD FERGUSONS COVE RD guiderail and retaining wall WEST 18 05-May-03 05-May-03 13-Jun-03 26-May-03 100%
FIELD COURT WESTMOUNT TO END new paving EAST 4   01-Jun-03   15-Jul-03 100%
GARDEN DRIVE VICTORIA TO SLAYTER, S sidewalk renewal EAST 10 30-May-03 30-May-03 11-Jul-03 17-Jul-03 100%
GEORGE STREET PELZANT TO DAWSON, W sidewalk renewal EAST 10 30-May-03 30-May-03 11-Jul-03 17-Jul-03 100%
GEORGE STREET PINEHILL TO SCHOOL new sidewalk CENTRAL 20 30-Jun-03 30-Jun-03     74%
GLADSTONE AVENUE VICTORIA TO END paving renewal EAST 10 11-Aug-03 11-Aug-03 9-Sep-03 24-Sept-03 100%
GLADSTONE STREET WINDSOR TERRACE TO ALMON, W sidewalk renewal WEST 11 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
GLENDALE ROAD EDGEWOOD TO ROSLYN, W sidewalk renewal WEST 11 23-Jun-03   04-Aug-03 13-Aug-03 100%
GOUROK STREET CULRAIN TO CIVIC 58 pavement resurfacing EAST 6 02-Jun-03 02-Jun-03 15-Jul-03 11-Jul-03 100%
GREBE AVENUE HIGHWAY 3 TO CIVIC 19 new paving CENTRAL 22 17-Jun-03 18-Jun-03 14-Jul-03 02-Jul-03 100%
GREENWOOD AVENUE ROXTON TO END, E sidewalk renewal WEST 13 23-Jun-03   04-Aug-03 13-Aug-03 100%
GUYSBOROUGH AVENUE SHAWINIGAN TO CIVIC 20 pavement resurfacing EAST 7 28-May-03 28-May-03 9-Jul-03 21-Jul-03 100%
HAMMONDS PLAINS RD AT BLUEWATER intersection improvements CENTRAL 21   28-Jul-03     100%
HARRIS STREET MAYNARD TO AGRICOLA paving renewal WEST 12         0%
Harvard St., Hfx. Chebucto to Quinpool watermain cleaning & lining WEST 14          
HERRING COVE ROAD AT ARMSHORE retaining wall WEST 17 08-Sep-03 08-Sep-03 10-Oct-03 19-Dec-03 100%
HERRING COVE ROAD ROTARY TO PURCELLS COVE ROAD traffic improvements WEST 17 09-Jun-03 09-Jun-03   10-Oct-03 100%
HERSHEY ROAD ESSON TO CLYDE sidewalk renewal EAST 8 11-Aug-03 11-Aug-03 09-Sep-03 24-Sep-03 100%
HIGHLAND CRESCENT / ESTELLE STREET POPLAR TO END paving renewal EAST 4 20-Aug-03 20-Aug-03 14-Nov-03 14-Nov-03 92%
HILLSIDE AVENUE LAKEVIEW TO CRICHTON, S sidewalk renewal EAST 10 30-May-03 30-May-03 11-Jul-03 17-Jul-03 100%
HINES ROAD STORM SEWER storm sewer EAST 5,8   01-Apr-03   01-May-03 100%
HINES ROAD TRUNK SEWER REPLACEMENT, PHASE 2 & 3 stormwater control EAST 5,8   15-Feb-03   01-Jun-03 100%
HORSESHOE ISLAND RETAINING WALL retaining wall WEST 14 26-Sep-02 28-Oct-02 31-Oct-02 10-Jun-03 100%
HUGH ALLEN DRIVE COLE HARBOUR TO EVERGREEN pavement resurfacing EAST 4 20-Aug-03 20-Aug-03 14-Nov-03 14-Nov-03 25%
HUGH ALLEN DRIVE AREA - STORM SEWER HIGHLAND, ESTELLE, EVERGREEN, HUGH ALLEN storm sewer EAST 4 20-Aug-03 20-Aug-03 14-Nov-03 14-Nov-03 20%
HYDROSTONE LANES ISLEVILLE TO NOVALEA sewer lining WEST 11 01-Nov-02 01-Nov-02 06-Dec-02   100%
HYLAND ROAD VIEW TO LEAMONT new paving EAST 10 03-Sep-02   24-Sep-02   100%
ISLEVILLE STREET STANLEY TO COLUMBUS, E sidewalk renewal WEST 11 02-Sep-03   01-Oct-03    
JABARO LANE GREBE TO END new paving CENTRAL 22 17-Jun-03 18-Jun-03 14-Jul-03 02-Jul-03 100%
JAMIESON STREET WINDMILL TO DILLMAN paving renewal EAST 9 11-Sep-03 06-Oct-03 23-Oct-03 19-Dec-03 100%
JOSEPH HOWE DRIVE AT BAYERS ROAD traffic improvement WEST 15 23-Jan-03 01-Feb-03 16-May-03 11-May-03 100%
JUBILEE ROAD CONNAUGHT TO CAMBRIDGE traffic improvement WEST 13 20-Aug-03 18-Aug-03 15-Oct-03 14-Nov-03 98%
JUNIPER CRESCENT LEIBLIN PARK TO LEIBLIN PARK new storm sewer WEST 18 SPRING 2004        
KEARNEY LAKE ROAD KEARNEY LAKE ROAD guiderail WEST 16          
KEARNEY LAKE ROAD KEARNEY LAKE ROAD retaining wall WEST 16 22-Sep-03 30-Oct-03 25-Oct-03 21-Nov-03 98%
LACEWOOD DRIVE PHASE 1, UPGRADES curb, sidewalk, widening WEST 16 28-Oct-02 04-Nov-03 29-Nov-02 01-Dec-03  
LACEWOOD DRIVE BI-HI TO CHAIN LAKE DRIVE new sidewalk WEST 16          
LAKE MAJOR ROAD Lake Major Road (Governor Rd. to Downie Rd.) new sidewalk EAST 3          
LAKESIDE TERRACE CRICHTON AVENUE TO END paving renewal EAST 10 03-Oct-02 03-Oct-02 14-Nov-02 15-Jul-03 100%
Lawrence St., Hfx. Harvard to Windsor watermain cleaning & lining WEST 14          
LITTLE SACKVILLE RIVER STORMWATER CONTROL sidewalk renewal CENTRAL 19,20 SPRING 2003 04-Aug-03 15-Sep-03   99%
LOWER WATER STREET BRICK SIDEWALK REPLACEMENT NEW SIDEWALK WEST 12 13-Oct-03   24-Nov-03   98%
McINTOSH RUN - SANITARY SEWER OLD SAMBRO RD TO HERRING COVE storm sewer WEST 18 12-Aug-02 12-Aug-02 20-Sep-02   88%
McLENNAN AVENUE COLINDALE TO GLENORA pavement resurfacing WEST 17 20-Aug-02 20-Aug-02 15-Oct-02   60%
MICMAC STREET REGENT TO CIVIC 3458, W sidewalk renewal WEST 11 24-Jun-03 24-Jun-03 08-Aug-03 08-Aug-03 100%
MILLWOOD DRIVE CIVIC 388 TO BEAVERBANK pavement resurfacing CENTRAL 19          
MILLWOOD DRIVE CIVIC 388 TO BEAVERBANK, NE new sidewalk CENTRAL 19         60%
Monastery Ln., Hfx. Allan to Quinpool watermain cleaning & lining WEST 14          
NORMANDY DRIVE LEAMAN TO NOVALEA, N sidewalk renewal WEST 11 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
NORTH PRESTON SEWAGE TREATMENT PLANT EXPANSION plant expansion EAST 4          
NORTH STREET North Street / Chebucto Road Intersection traffic improvement EAST 11/14 18-Nov-01 18-Nov-01   02-Sep-03 100%
OAKLAND ROAD ROBIE TO BEAUFORT sewer lining WEST 13 01-Nov-02 01-Nov-02 06-Dec-02   100%
OLD MILLER ROAD COLERIDGE TO CIVIC 10 OLD MILLER new paving EAST 4   01-Jun-03   15-Jul-03 100%
OLD SAMBRO ROAD SUSSEX TO MacINTOSH BRIDGE storm sewer WEST 18 21-Aug-02 21-Aug-02 02-Oct-02 15-Aug-03 100%
PARKDALE AVENUE ROYAL PINE TO FIELDING paving WEST 17 20-Aug-03 20-Aug-03 15-Oct-03 03-Nov-03 90%
PLEASANT STREET ATLANTIC TO IRVING - SANITARY SEWER sanitary sewer EAST 8 01-Nov-02 01-Nov-02 06-Dec-02 01-Feb-03 100%
PRATT & WHITNEY DRIVE AEROTECH TO END 2nd lift of asphalt CENTRAL 2 24-Jul-03 28-Jul-03 04-Sep-03 17-Oct-03 99%
PURCELL'S COVE RD. / WILLIAMS LK RD. PURCELLS COVE ROAD & WILLIAMS LAKE RD traffic improvement WEST 17         100%
RA5 REPLACEMENTS VARIOUS LOCATIONS traffic improvement WEST var. 19-Jun-03 06-Jun-03 18-Aug-03   100%
REGAL ROAD DORTHEA TO CIVIC 84 paving resurfacing EAST 7 28-May-03 28-May-03 9-Jul-03 21-Jul-03 100%
REGIONAL TRAILS DEVELOPMENT REGATTA POINT paving WEST 17          
Renfrew St., Dart. Pleasant to Glenview watermain cleaning & lining EAST 8 18-Aug-03 18-Aug-03      
ROBERT MURPHY DRIVE DOUG SMITH TO PETER LOWE resurfacing WEST 14 SPRING 2004      
ROBIE STREET MERKEL TO CABOT, W sidewalk renewal WEST 11 02-Sep-03   01-Oct-03    
ROBIE STREET WIDENING CUNARD TO GARRICK traffic improvement WEST 12          
ROCKY HILL ROAD TREMONT TO FOREST HILL paving WEST 16 09-Jul-03 09-Jul-03 21-Aug-03 CANCELLED CANCELLED
ROLAND AVE. / JAMES ST. ST.MARGARETS BAY RD TO SCHOOL ENT. new sidewalk WEST 22          
ROSE STREET PINE TO BEECH sewer lining EAST 10 15-Sep-03 15-Sep-03 10-Oct-03   40%
ROSS ROAD Ross Road Area sewer lining EAST 4          
ROSS ROAD GREEN VALE TO CIVIC 256/264 paving resurfacing EAST 4 29-May-03 29-May-03 11-Jul-03 23-Jun-03 100%
ROYAL PINE AVENUE SOMERSET TO MURDOCH, E sidewalk renewal WEST 17 24-Jun-03 24-Jun-03 08-Aug-03 08-Aug-03 100%
RUFUS AVENUE BIRCH TO DUTCH VILLAGE pavement resurfacing WEST 15   13-Oct-03     65%
RUTLEDGE STREET FREDERICK TO END resurfacing CENTRAL 21 16-Jul-03 16-Jul-03 27-Aug-03   95%
RUTLEDGE STREET FREDERICK TO SHOREVIEW new sidewalk CENTRAL 21 16-Jul-03 16-Jul-03 27-Aug-03   100%
SERPENTINE AVENUE MONTAGUE TO SMALLWOOD new sidewalk CENTRAL 4   01-Jun-03   15-Sep-03  
SERPENTINE / CODROY AVENUE MONTAGUE TO END paving resurfacing CENTRAL 4   01-Jun-03   15-Sep-03  
SHIRLEY STREET ROBIE TO VERNON, N sidewalk renewal WEST 13 23-Jun-03   4-Aug-03 13-Aug-03 100%
SHORE ROAD OCEANLEA TO SHOREVIEW new sidewalk EAST 5 08-Sep-03 08-Sep-03 20-Oct-03   100%
SHORE ROAD BANK STABILIZATION - VARIOUS LOCATIONS sewer lining EAST 5 13-Nov-02 13-Nov-02 24-Dec-02 16-Jul-03 100%
SKYRIDGE AVENUE KAYE TO PRINCE new sidewalk CENTRAL 20 30-Jun-03 30-Jun-03     95%
SKYRIDGE AVENUE PRINCE TO KAYE paving resurfacing CENTRAL 20 30-Jun-03 30-Jun-03     95%
SLAYTER STREET SCHOOL TO SHAMROCK, W sidewalk renewal EAST 10 30-May-03 30-May-03 11-Jul-03 17-Jul-03 100%
SOUTH STREET EDWARD TO HENRY, N sidewalk renewal WEST 13 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
SOUTH STREET ROBIE TO EDWARD, N sidewalk renewal WEST 13 05-May-03 05-May-03 13-Jun-03 13-Jun-03 100%
STAIRS STREET WINDMILL TO BEDFORD, SANITARY LINING sanitary sewer EAST 10 01-Nov-02 01-Nov-02 06-Dec-02   100%
STANFORD STREET ERNST TO OAKLEIGH, E sidewalk renewal WEST 17 24-Jun-03 24-Jun-03 08-Aug-03 08-Aug-03 100%
STONE CREST COURT STONEMOUNT TO END new paving CENTRAL 20   09-Jul-03 23-Jul-03 28-Jul-03 95%
STONEMOUNT DRIVE EXISTING TO LAKEVIEW new paving CENTRAL 20   09-Jul-03 23-Jul-03 28-Jul-03 95%
ST. MARGARETS BAY ROAD GOVERNORS TO WILBERT DEVOE,NE new sidewalk WEST 17 08-Sep-03   17-Oct-03   95%
SUNNYDALE CRESCENT ROCKY LAKE TO ROCKY LAKE paving renewal CENTRAL 21   17-Oct-03     20%
SUNNYDALE CRESCENT ROCKY LAKE TO ROCKY LAKE, N new sidewalk CENTRAL 21   17-Oct-03     20%
SURFACE SEALING VARIOUS LOCATIONS surface sealing ALL         20-Sep-02 100%
TAMARACK CIRCLE, SACKVILLE GLENDALE TO CIVIC 95 sewer project CENTRAL 20 02-Jul-03 02-Jul-03   11-Jul-03 100%
TARTAN AVENUE AUBURN TO ATHLONE new paving WEST 18 20-Aug-03 20-Aug-03 15-Oct-03 15-Oct-03 100%
TRAFFIC SIGNAL REHABILITATION BEDFORD HWY TO HAMMONDS PLAINS RD traffic improvement CENTRAL 21 8-Aug-03 12-Aug-03     95%
TREMONT DRIVE BEDFORD HWY TO END paving resurfacing WEST 16 09-Jul-03 09-Jul-03 21-Aug-03   98%
TUPPER STREET PLEASANT TO HARBOUR paving resurfacing EAST 8 02-Jun-03 02-Jun-03 15-Jul-03 11-Jul-03 100%
UNIACKE STREET GOTTIGEN TO BRUNSWICK new paving WEST 12   08-Oct-03 05-Dec-03 05-Dec-03 98%
WEST STREET AGRICOLA TO MAYNARD, N sidewalk renewal WEST 12 02-Sep-03   01-Oct-03    
WESTMOUNT DRIVE CIVIC 31 TO EXISTING PAVEMENT new paving EAST 4   01-Jun-03   15-Jul-03 100%
WILLIAM NELSON DRIVE KINSAC TO END new paving CENTRAL 19 9-Jul-03 9-Jul-03 23-Jul-03 28-Jul-03 99%
WINDSOR STREET EDINBURGH TO LONDON, W sidewalk renewal WEST 11 02-Sep-03   01-Oct-03    
WINDSOR STREET CORK TO YOUNG, E sidewalk renewal WEST 11 05-May-03   13-Jun-03    
WOODLAND AVENUE AT VICTORIA ROAD traffic signal upgrade EAST 9 11-Aug-03 16-Sep-03 22-Sep-03 12-Dec-03 100%
WRIGHT AVENUE AT MacDONALD intersection improvements EAST 9   30-Jul-03     100%
Yale St., Hfx. Harvard to Monestary Ln. watermain cleaning & lining WEST 14          
Yukon St., Hfx. Harvard to Monestary Ln. watermain cleaning & lining WEST 14          
ZONE 1, JUAN DAMAGE VARIOUS LOCATIONS sidewalk replacement WEST           100%
ZONE 2, JUAN DAMAGE VARIOUS LOCATIONS sidewalk replacement WEST           100%
ZONE 3, JUAN DAMAGE VARIOUS LOCATIONS sidewalk replacement WEST           100%
ZONE 1-E, JUAN DAMAGE VARIOUS LOCATIONS sidewalk replacement EAST           100%
ZONE 2-E, JUAN DAMAGE VARIOUS LOCATIONS sidewalk replacement EAST           100%