Location of Work
HALIFAX |
Description of Work |
| Halifax South Sewage Collection System(SCS) |
Diversion Piping underway at various CSOs.
Salter Street Outfall Pipe reinstatement complete except for timber curbing.
|
| Balmoral Pumping Station |
No construction activity.
|
| Pier A Pumping Station |
Monorail installed, electrical circuit and hook-up complete, no breaker installed yet.
|
| Atlantic School of Theology(AST) Pumping Station |
No construction activity.
|
| Duffus Street Pumping Station |
Control wiring continues
Momorail and crane installations ongoing.
Heater being installed for relocated water service. Water meter installation to follow.
|
| Maritime Museum of the Atlantic CSO(combined sewer overflow) |
Diversion piping to proceed after Sackville Street CSO diversion piping.
|
| Halifax North SCS |
No construction activity.
|
| Irving Wharf |
Stockpile site decommissioned.
|
| Halifax Wastewater Treatment Facility(WWTF) Outfall |
Repairs by Wilcraft upcoming.
|
| Upper Water St. CSO |
Placing pipe from CSO towards connection manhole.
New manhole placed.
Traffic diversion in place.
CSO dewatering ongoing.
|
| Duke St. Sewer Separation |
No construction activity. |
| Salter St. Sewer Separation |
No construction activity. |
| Lower Water St. Sewer Separation |
No construction activity.
|
| Cogswell St. Entrance Shaft |
No construction activity. |
| SCADA System |
Repeater at Cowie Hill has been fabricated, no installation date yet.
SCADA antennas are now installed on all Halifax pumping stations.
|
| Halifax Access Tunnel Site-under Cogswell St. interchange |
No construction activity.
|
| Sackville St Tunnel exit Shaft Site |
No construction activity. |
| Sackville Street CSO |
Diversion piping continues.
Lower and upper sections of inlet connection poured.
Installation of new temporary manhole to route flow from Hollis St into CSO upcoming.
Traffic diversion in place. |
| DND Parking Matters |
No displaced parking.
|
| North Street CSO |
No construction activity.
|
| Young Street CSO |
No construction activity.
|
| |
|
Location of Work
DARTMOUTH |
Description of Work |
| Dartmouth WWTF Outfall |
No construction activity.
|
Dartmouth WTP Access Driveway |
No construction activity.
|
| Cuisack St. CSO |
No construction activity.
|
| Dartmouth Cove Mainline Pipe |
Internal work ongoing in drain manholes and air release valve chambers.
|
| Maitland St. CSO |
No construction activity.
|
| Wallace St. CSO |
No construction activity.
|
| Jamieson St. CSO |
No construction activity.
|
| Jamieson St. PS |
Final ductback to road and SCADA outstanding.
Diversion piping on hold pending design of repairs to existing combined sewer and outfall.
Vent piping from CSO chamber to Pumping Station complete.
|
| Dartmouth South Mainline Pipe |
Air release and drain manholes are installed, internals ongoing.
|
| Alderney Drive |
Formed and poured curb in boulevard, some reinstatement remains.
|
| Dartmouth North Mainline Pipe |
No construction activity.
|
| Melva St PS |
Main power feed/primary ductbank from power pole to transformer pad complete.
|
| Park Avenue Pumping Station |
Mechanical and electrical work ongoing, HVAC complete.
No pumps installed yet.
Civil deficiencies and paint touch-ups outstanding.
Vent connection between the CSO and PS complete.
|
Shore Road |
Lyle Street Diversion piping testing ongoing.
Repairs to existing 450 diam. concrete pipe outstanding.
|
| Ferguson Road CSO |
Mechanical and electrical work substantially complete.
|
| Lyle St CSO |
Pipe testing ongoing.
|
| Tupper St. Sewer Separation |
No construction activity.
|
| Park Ave. CSO |
No construction activity.
|
| Old Ferry Road CSO |
No construction activity. |
| Grove St. CSO |
Final power connection outstanding, new pole required.
|
| King St. CSO |
Ductbanks are complete, pulling of primary lines upcoming.
Curb and sidewalk work underway.
|
| |
|
Location of Work
HERRING COVE
|
Description of Work |
Herring Cove WWTF Access Road |
Power poles installed.
No construction activity. |
Herring Cove WWTF Outfall |
Offshore survey complete, and location established.
Design being reviewed by engineer.
|
| Herring Cove SCS Pressure Sewer |
No construction activity.
|
| Roaches' Pond Retention Tank |
Installation of sheet pile for coffer dam complete.
Excavation and whaler installation underway. |
| Herring Cove Pumping Station |
No construction activity.
|
| |
|
Location of Work
AEROTECH PARK |
Description of Work |
| Biosolids Processing Facility BPF Building |
Completion of deficiencies underway.
Building Substantially Complete.
Preparations for commissioning underway.
|