Major construction on the Harbour Solutions Project began in November of 2003. The table below highlights the major components of the project.

Project Component Construction Start Completion
Halifax SCS November 2003 Summer 2007
Halifax WWTF Fall 2004 Summer/Fall 2007
Dartmouth SCS Late Spring 2005 Fall/Winter 2007
Dartmouth WWTF Spring 2005 Spring/Summer 2008
Herring Cove SCS

Summer/Fall 2006

Summer/Fall 2008
Herring Cove WWTF Spring 2006 Fall/Winter 2008
Biosolids Processing Facility Fall 2005 Summer 2007

*SCS = sewage collection system

*WWTF = wastewater treatment facility