Major construction on the Harbour Solutions Project began in November of 2003. The table below highlights the major components of the project.
| Project Component |
Construction Start |
Completion |
| Halifax SCS |
November 2003 |
Summer 2007 |
| Halifax WWTF |
Fall 2004 |
Summer/Fall 2007 |
| Dartmouth SCS |
Late Spring 2005 |
Fall/Winter 2007 |
| Dartmouth WWTF |
Spring 2005 |
Spring/Summer 2008 |
| Herring Cove SCS |
Summer/Fall 2006 |
Summer/Fall 2008 |
| Herring Cove WWTF |
Spring 2006 |
Fall/Winter 2008 |
| Biosolids Processing Facility |
Fall 2005 |
Summer 2007 |
*SCS = sewage collection system
*WWTF = wastewater treatment facility