Construction activities related to the Harbour Solutions Project Sewage Collection System (SCS) and Wastewater Treatment Plant (WTP) sites.
| Start |
Location |
Work |
Approximate Duration |
| April 2004 |
HRM land, Cogswell St. Interchange |
Tunnel access shaft |
1 month |
|
Lower Water St @ Maritime Museum of the Atlantic |
Combined sewer overflow (CSO) chamber |
3 months |
|
Hollis St from Sackville St to Morris St |
main collection line |
4 months |
|
DND property from Cornwallis to North St |
main collection line |
3 months |
|
Sackville St from Lower Water to Hollis St |
Tunnel access shaft & CSO chamber |
6 months |
| May 2004 |
DND property from North St to Young St |
main collection line |
3 months |
|
Tunnel through Halifax CBD from Cornwallis St to Sackville St |
Tunnel |
12 months |
|
Atlantic School of Theology |
pumping station |
8 months |
| June 2004 |
Todd property corner of Inglis and Barrington St. |
pumping station |
9 months |
|
Inglis St from Barrington to Young Ave |
main collection line |
3 months |
| July 2004 |
HRM property off Upper Water St @ Casino |
CSO chamber |
3 months |
| August 2004 |
Young Ave from Inglis to Southwood Dr. |
main collection line |
2 months |
|
Barrington St from Morris to Inglis St |
main collection line |
4 months |
| September 2004 |
Pine Hill Dr from Tower Rd to Francklyn St |
main collection line |
3 months |
|
Utility bridge Tower Rd @ Southwood Dr. |
main collection line |
4 months |
|
Point Pleasant Park Balmoral pump station |
pump station |
4 months |
| October 2004 |
HRM property Historic Properties |
CSO chamber |
3 months |
|