Location of Work Description of Work
| Halifax South Sewage Collection System(SCS) |
Halifax South SCS (Duke and Lower Water St.)
- No construction activity.
Halifax South SCS (Hollis)
- Local traffic only between Morris and South.
- Installation of new sanitary sewer for sewer separation is proceeding.
Halifax South SCS (Morris)
- No construction activity (basic sewer work completed).
Halifax South SCS (Barrington)
- No construction activity.
Halifax South SCS (Inglis)
- No construction activity (basic sewer work complete).
Halifax South SCS (Young Ave.)
- No construction activity (basic sewer work completed).
Halifax South SCS (Southwood)
- No construction activity (basic sewer work complete).
Halifax South SCS (CN Pipe Bridge)
- No construction activity.
Halifax South SCS (Pine Hill)
- No construction activity.
Halifax South SCS (Francklyn)
- Asphalt cap complete.
- No construction activity.
|
| Balmoral Pumping Station |
Washroom substantially complete.
Mechanical and electrical installations continue. |
| Pier A Pumping Station |
Pump station is backfilled.
Shoring extraction complete.
Sheeting/shoring placement for CSO proceeding with excavation and installation of walers. |
| Atlantic School of Theology(AST) Pumping Station |
Installation of mechanical and electrical equipment continues.
|
| Maritime Museum of the Atlantic CSO(combined sewer overflow) |
Installation of mechanical and electrical equipment in the CSO structure continues. |
| Halifax North SCS |
Traffic diversions at Duffus St. and Hanover St. for pipe installations. |
| Irving Wharf |
Stockpiled slate material on site. |
| Halifax Wastewater Treatment Plant(WTP) Outfall |
Upper Water St. open to traffic in front of Casino.
Pipe work proceeding across Barrington St. towards Halifax WTP.
|
| Upper Water St. CSO |
Upper Water St. reinstated for traffic.
Cleaning and preparing CSO for visual inspection. |
| Halifax Access Tunnel Site-under Cogswell St. interchange |
No construction activity. |
| Sackville St Tunnel exit Shaft Site |
No construction activity. |
| Sackville Street CSO |
Mechanical and electrical installations in CSO structure continue.
|
| DND Parking |
No displaced parking. |
| North Street CSO |
Mechanical and electrical installations in CSO structure continue. |
| Young Street CSO |
Installation of mechanical and electrical equipment in CSO structure continues. |
| Halifax WTP Site |
Drilling/blasting around tunnel entrance for transition into wet well.
Roof bolting proceeding in tunnel entrance.
Floor anchors in north end of wet well installed and stressed.
Walls and slabs in Zones 2 and 3 proceeding.
Mechanical and electrical piping proceeding in Zones 2 and 3. |
| Dartmouth WTP Outfall |
No current activity. |
| Duke St. Sewer Separation |
Reinstatement of Duke St. underway. |
Terminal Road |
No construction activity. |
Cogswell St. Entrance Shaft |
No current activity. |
| Young St. Outfall |
Site reinstated and repaved.
No construction activity. |
Dartmouth WTP Access Driveway |
Grubbing and grading essentially complete.
Construction of retaining wall proceeding. |
Dartmouth North SCS |
Trenching and preparing for pipe installation between Grove and Wallace St. is complete.
Pipe placement proceeding. |
Dartmouth WTP Site |
Base lift of fill material placed to raise grade around building footprint. |
| Salter St. Sewer Separation |
Asphalt cap complete on Granville and Salter.
Hollis St. pipe installations continue between Morris and South. |
| Cuisack St. CSO |
Steel sheet pile shoring installation complete.
Portion of the Dartmouth waterfront trail diverted around CSO site.
Currently forming CSO walls. |