Underground Overhaul Project Updates

- Zone 1 - Quinpool
(MH 1 - 27)
Zone 2 - South
(MH 27 - 53)
Zone 3 Belmont
(MH 53 - 76)
Zone 4 - AST
(MH 76 - 93)
Cleaning period June 20th -
June 28th
June 29th -
Aug 12th
July 11th -
July 19th
July 20th -
Aug 1st
Access and general construction works June 20th -
Aug 21th
June 29th -
Sept 5th
June 30th -
Sept 22nd
July 3rd -
Oct 6th
Pipe prep work Aug 15th -
Aug 23th
Sept 8th -
Sept 13th
Oct 10th -
Oct 18th
Nov 4th -
Nov 9th
Lining Aug 18th -
Aug 29th
Sept 11th -
Sept 27th
Oct 13th -
Oct 30th
Nov 7th -
Nov 23rd
Restoration Aug 25th -
Sept 18th
Sept 19th -
Oct 6th
Oct 23rd -
Nov 23th
Nov 16th -
Dec 4th