Permit Volume & Processing Times

The municipality’s permit processing times are a calculation of the number of calendar days between when the application is submitted by the customer and when the permit is issued. Permit processing times are shown as an average and are inclusive of both staff time as well as customer time with the application. 

Residential Building Permits

(New Builds, Additions or Renovations to Low Density/6 units or less Residential)
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25

734 Permits Submitted
604 Permits Issued

2358 Permits Submitted
2030 Permits Issued

16 avg # days to issue
(of those submitted within past 3 months)

22 avg # days to issue

Mixed Use and Commercial Building Permits

(New Builds, Additions or Renovations to Commercial Buildings & Large-Scale/High Density Residential)
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25

132 Permits Submitted
137 Permits Issued

622 Permits Submitted
561 Permits Issued

21 avg # days to issue
(of those submitted within past 3 months)

35 avg # days to issue

Construction Permits

(Occupancy, Deck, Demolition, Fence, Mobile Home, Sign, Solar, Pool)
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25

753 Permits Submitted
627 Permits Issued

2514 Permits Submitted
2246 Permits Issued

9 avg # days to issue
(of those submitted within past 3 months)

10 avg # days to issue

Engineering Permits

(Blasting, Development - Right of Way, Grade Alteration, Lot Grading)
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25

556 Permits Submitted
494 Permits Issued

1763 Permits Submitted
1460 Permits Issued

12 avg # days to issue
(of those submitted within past 3 months)

21 avg # days to issue

Land Use Approval Permit

(Development Only)
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25
Rolling previous 3 months: Apr 1/25 - July 1/25 Rolling Year: July 1/24 - July 1/25

291 Permits Submitted
193 Permits Issued

1284 Permits Submitted
960 Permits Issued

17 avg # days to issue
(of those submitted within past 3 months)

24 avg # days to issue

Residential Unit Volumes

Approved and Pending Units

Year-over-Year
YEAR Units Approved Units Pending
YEAR Units Approved Units Pending
2025 1089

17.64% of previous years' units approved

5378
2024 6173

96.39% of previous years' units approved

3012
2023 6404

108.47% of previous years' units approved

3245
2022 5904

144.07% of previous years' units approved

2819
Number of Residential units issued by Structure Type

Number of Residential units issued by Structure Type