Bus Stop Construction

2024/2025 Bus Stop Construction

A list of current plans for bus stop construction, adjustments and improvements by district. To look up your district, enter your street address into our District Look-up tool. If you have any questions, or to report any issues (i.e., drainage or sewer lateral issues) please contact 311.

Please note: If your district is not listed, there is no construction planned for 2024/2025.

Bus Stop Location Nearest Civic Address(es) Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address(es) Location of Work Scope of Work Status
Brooks Dr At East Preston Rec Centre (8929) 24 Brooks Dr West side of Brooks Dr abutting Civic 24 Slight relocation, new concrete pad, connection to multi-use path Started August 2024
Brooks Dr Opposite East Preston Rec Centre (8769) 11 Brooks Dr East side of Brooks Dr abutting Civic 11 Slight relocation, new elongated concrete pad Started August 2024
Hwy 7 After Civic 1776 (8767) 1776 Hwy 7 East side of Hwy 7 after the intersection at Old Preston Rd Relocation at the location of work Construction starting September 2024
Hwy 7 After Glasgow Rd (2340) 1900 Hwy 7 South side of Hwy 7 abutting Civic 1900 New stop with concrete pad and concrete sidewalk Construction starting September 2024
Hwy 7 After Old Preston Rd (2339) Opposite to Civic 1799 East side of Hwy 7 after the intersection at Old Preston Rd New stop, concrete pad, sign post in between of the curb and sidewalk, and concrete sidewalk Construction starting September 2024
Hwy 7 After Upper Governor St (8930) 1977 Hwy 7 Northwest side of Hwy 7 abutting Civic 1977 New concrete bus pad, connection to multi-use path Construction starting September 2024
Hwy 7 At Civic 1799 (8931) 1799 Hwy 7 West side of Hwy 7 abutting Civic 1799 Relocation, new concrete bus pad, connection to multi-use path Construction starting September 2024
Hwy 7 Before Circle Dr (8918) 3293 Hwy 7 North side of Hwy 7 abutting Civic 3293 Widened gravel shoulder, new asphalt pad Construction starting October 2024
Hwy 7 Before Glasgow Rd (2341) 1905 Hwy 7 North side of Hwy 7 abutting Civic 1905 New stop with concrete pad Construction starting September 2024
Hwy 7 Before Lower Governor St (8768) 1 Lower Governor St Southeast side of Hwy 7 adjacent 1 Lower Governor St Slight relocation of stop, installation of a concrete pad and new sign Construction starting September 2024
Hwy 7 Before Martin Lake Dr (8920) 3103 Hwy 7 West side of Hwy 7 abutting Civic 3103 Widened gravel shoulder, new asphalt pad Construction started September 2024
Bus Stop Location Nearest Civic Address(es) Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address(es) Location of Work Scope of Work Status
Windward Ave After Lucien Dr (2262) 37 Windward Ave North side of Windward Ave New concrete pad between curb and sidewalk Completed September 2024
Belle Vista Dr After Spring Ave (6294) 73 Belle Vista Dr South side of Belle Vista Dr near Civic 73 New concrete pad between curb and sidewalk Construction started September 2024
Caldwell Rd After Birchill Dr (2218) 1720 Birchill Dr Northeast side of Caldwell Rd abutting Civic 1720 New concrete landing pad and sidewalk connection to Birchill Dr Construction starting September 2024
Caldwell Rd after Cow Bay Rd (6333) Opposite to 1804 Caldwell Rd West side of Caldwell Rd near the cemetery Upgrades to shelter pad Completed September 2024
Caldwell Rd After Himmelman Dr (6334) 49 Sidney Cr West side of Caldwell Rd after Himmelman Dr abutting 49 Sidney Cr Upgrades to bus pad length Completed September 2024
Caldwell Rd After Thorncrest Ct (6337) 1881 Caldwell Rd West side of Caldwell Rd near the elementary school Upgrades to shelter pad Completed September 2024
Caldwell Rd Before Deyoung Dr (2220) 1622 Caldwell Rd Northeast side of Caldwell Rd abutting Civic 1622 New concrete landing pad and sidewalk connection to Deyoung Dr Construction starting September 2024
Caldwell Rd Before Seabreeze Dr (6340) 1909 Caldwell Rd Southwest side of Caldwell Rd near the senior's residence Upgrades to shelter pad Completed September 2024
Caldwell Rd Opposite Kaleigh Dr (2219) 1682 Caldwell Rd Northeast side of Caldwell Rd abutting Civic 1682 Concrete landing pad with sidewalk connection to Kaleigh Dr Construction starting September 2024
Collins Grv After Spring Ave (2267) 103 Collins Grv West side of Collins Grv adjacent 103 Collins Grv New concrete pad between curb and sidewalk Completed July 2024
Collins Grv At Civic 83 (2268) 83 Collins Grv West side of Collins Grv abutting Civic 83 New concrete pad between curb and sidewalk Completed July 2024
Collins Grv Before Collins Grove Rg (2269) 1 Collins Grove Rg South side of Collins Grv adjacent 1 Collins Grove Rg New concrete pad between curb and sidewalk Pending 2024 construction
Cow Bay Rd Before Caldwell Rd (8674) 386 Cow Bay Rd Northwest side of Cow Bay Rd abutting Civic 386 Concrete landing pad and sidewalk connection to intersection at Caldwell Rd Pending 2024 construction
Gregory Dr Before Wildwood Blvd (6794) Opposite to 14 Gregory Dr North side of Gregory Dr opposite Civic 14 New concrete pad, sidewalk, and shelter pad Completed August 2024
Heritage Hills Dr Before Cow Bay Rd (8673) 4 Heritage Hills Dr Northeast side of Heritage Hills Dr abutting Civic 4 Concrete landing pad and sidewalk connection to Cow Bay Rd Construction starting September 2024
Heritage Hills Dr Before Serop Cr (8672) 1 Serop Cr Northeast side of Heritage Hills Dr adjacent 1 Serop Cr Concrete landing pad and sidewalk connection to Serop Cr Construction starting September 2024
Main Rd After Howard Ave (8012) 1095 Main Rd West side of Main Rd near Civic 1095 Slight relocation of bus stop with new concrete pad between curb and sidewalk Completed July 2024
Main Rd Before Bonaventure St (7486) 2 Hines Rd Northeast side of Main Rd near Bonaventure St Shelter replacement Completed January 2024
Portland Hills Terminal Bay 8 (8957) 866 Portland St Portland Hills Terminal Shelter replacement Completed September 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Circassion Dr After Ellerslie Cr (2307) 62 Circassion Cr West side of Circassion Dr abutting Civic 62 Relocation of Stop Circassion Dr Before Ellerslie (6425) to after Ellerslie Cr, new concrete pad between curb and sidewalk Completed August 2024
Cole Harbour Rd At Civic 1722 (2343) 1722 Cole Harbour Rd Northeast side of Cole Harbour Rd near Civic 1722 New bus stop created Construction starting November 2024
Cole Harbour Rd Before Dorothea Dr (6481) 907 Cole Harbour Rd North side of Cole Harbour Rd opposite Civic 912 Shelter replacement Completed May 2024
Cole Harbour Rd Opposite to Pacific Ave (2342) 1697 Cole Harbour Rd West side of Cole Harbour Rd near Civic 1697 New bus stop created Construction starting November 2024
Cole Harbour Rd After Otago Dr (6478) 915 Cole Harbour Rd North side of Cole Harbour Rd abutting Civic 915 Concrete bus pad repair Completed August2024
Flying Cloud Dr Before Gregory Dr (2235) 204 Flying Cloud Dr West side of Flying Cloud Dr New bus stop, concrete pad, and sidewalk Completed August 2024
Forest Hills Pky At Cole Harbour Place (6669) 51 Forest Hills Pky East side of Forest Hills Pky abutting Civic 51 New shelter Completed March 2024
Gregory Dr After Flying Cloud Dr (6792) 7 Gregory Dr North side of Gregory Dr abutting Gregory Dr Park Removal of shelter and old pad, relocation of bus stop to 204 Flying Cloud Dr Completed August 2024
Main St After Cherry Brook Rd (6942) 10 Cherry Brook Rd North side of Main St abutting Civic 10 New shelter Completed August 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Lancaster Dr After Sea King Dr (2323) Opposite to 4 Cannon Terr West side of Lancaster Dr New concrete pad Completed August 2024
Micmac Blvd Before Horizon Ct (7211) 35 Micmac Blvd North side of Micmac Blvd near Civic 35 New concrete pad and sidewalk from bus pad to pedestrian ramp at the intersection of Micmac Blvd and Horizon Crt Construction starting October 2024
Pleasant St Before Prince Arthur Ave (9007) 205 Pleasant St East side of Pleasant St abutting Civic 205 Shelter replacement Completed March 2024
Pleasant St Before Southdale St (7485) 181 Pleasant St East side of Pleasant St abutting Civic 181 Shelter replacement Completed March 2024
Portland St After Gaston Rd (8038) 2 Nicole Ct East side of Portland St adjacent 2 Nicole Ct Shelter replacement Completed March 2024
Sea King Dr After Ernest Ave (8264) 2 Sea King Dr South side of Sea King Dr abutting 2 Sea King Dr Relocation of stop towards Ernest Ave, installation of landing pad and sidewalk Completed June 2024
Sea King Dr After Lancaster Dr (8263) 35 Sea King Dr North side of Sea King Dr adjacent 35 Sea King Dr Installation of concrete pad between curb and sidewalk Completed June 2024
Sea King Dr Before Ernest Ave (8266) 1 Sea King Dr North side of Sea King Dr abutting 1 Sea King Dr Installation of concrete pad between curb and sidewalk Completed June 2024
Sea King Dr Before Lancaster Dr (8265) 34 Sea King Dr South side of Lancaster Dr abutting 34 Sea King Dr Removal of bus stop and relocation at Lancaster Dr Completed June 2024
Thistle St After Beech St (8383) 74 Thistle St Southeast side of Thistle St abutting Civic 74 New concrete pad Pending 2024 construction
Thistle St After Crichton Park Rd (8384) 2 Forest Rd North side of Thistle St near 2 Forest Rd Upgrading bus pad length Pending 2024 construction
Thistle St After Mayflower St (8386) 98 Thistle St South side of Thistle St abutting Civic 98 New concrete pad that makes stop accessible Pending 2024 construction
Thistle St Before Crichton Park Rd (8391) 3 Crichton Park Rd West side of Crichton Park Rd near Civic 3 New concrete pad and sidewalk Pending 2024 construction
Thistle St Before Mayflower St (8388) 97 Thistle St North side of Thistle St abutting Civic 97 New and slightly larger concrete pad Pending 2024 construction
Thistle St Before Victoria Rd (8393) 85 Victoria Rd South side of the Thistle St adjacent Bicentennial School Slight relocation of stop, installation of concrete bus pad Pending 2024 construction
Thistle St opposite Beech St (8390) Opposite to 28 Beech St North side of the Thistle St opposite 28 Beech St Slight relocation of stop, installation of concrete bus pad Pending 2024 construction
Victoria Rd After Boland Rd (8419) 169 Victoria Rd South side of Victoria Rd abutting Civic 169 Shelter replacement Completed March 2024
Windmill Rd Opposite Pelzant St (8542) Opposite to 150 Windmill Rd West side of Windmill Rd opposite 150 Windmill Rd, adjacent DND Shelter replacement Competed September 2024
Windmill Rd Opposite Wallace St (8546) 269 Windmill Rd West side of Windmill Rd abutting Civic 269 Shelter replacement Completed August 2024
Woodland Ave After Slayter St (2306) 18 Woodland Ave East side of Woodland Ave abutting Civic 18 Relocation of Stop Woodland Ave Before Slayter St (8587), concrete pad between curb and sidewalk Completed August 2024
Woodland Ave Before Slayter St (2305) 21 Woodland Ave West side of Woodland Ave abutting Civic 21 Relocation of Stop Woodland Ave After Slayter St (8585), concrete pad between curb and sidewalk Completed August 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Akerley Blvd After Burnside Dr (6000) 140 Akerley Blvd South side of Akerley Blvd near Don Bayer Sports Field Sidewalk connection to existing bus pad to upgrade stop accessibility Construction starting September 2024
Albro Lake Rd Before Cedar Ct (6023) 174 Albro Lake Rd South side of Albro Lake Rd abutting Civic 174 New concrete pad, curb, and sidewalk Completed June 2024
Albro Lake Rd Before Chapman St (6020) 81 Albro Lake Rd North side of Albro Lake Rd adjacent Civic 85 Slight relocation, new concrete pad between curb and sidewalk Pending 2024 construction
Albro Lake Rd Rd After Cedar Ct (6017) 180 Albro Lake Rd North side of Albro Lake Rd opposite Civic 180 New concrete pad, curb, and sidewalk Completed June 2024
Appian Way Before Colonna Pl (2201) 67 Colonna Pl South side of Appian Way abutting Civic 67 New concrete pad and sidewalk connection Completed September 2024
Braemar Dr Before Creelman Dr (6312) 177 Braemar Dr West side of Braemar Dr adjacent Lake Micmac New concrete shelter pad Pending 2024 construction
Commodore Dr After Countryview Dr (8853) 9 Commodore Dr North side of Commodore Dr abutting Civic 9 New shelter Pending 2024 construction
Countryview Dr Before Shubie Dr (6797) 32 Foulis Row East side of Countryview Dr adjacent 32 Foulis Row New shelter Pending 2024 construction
Cutler Ave Before Civic 680 (2296) Civic 680 West side of Cutler Ave before Civic 680 New shelter March 2024 construction
Hudson Way Before Baffin Blvd (6083) No adjacent address Hudson Way east of Baffin Blvd New concrete pad, curb, and pedestrian ramp with tactile plates Pending 2024 construction
Ilsley Ave At Civic 121 (6958) 121 Ilsley Ave East side of Ilsley Ave abutting Civic 121 New concrete pad and sidewalk Construction started August 2024
Ilsley Ave Before MacDonald Ave (6959) 133 Ilsley Ave East side of Ilsley Ave abutting Civic 133 New concrete pad and sidewalk Construction started August 2024
Ilsley Ave Opposite Halifax Transit (6949) 133 Ilsley Ave East side of Ilsley Ave abutting Civic 133 New concrete pad and sidewalk Construction started August 2024
Leaman Dr Before Ambercrest Pl (2251) 24 Leaman Dr East side of Leaman Dr between Civic 24 and Ambercrest Pl New concrete pad and sidewalk Completed August 2024
Pinecrest Dr After Brule St (7451) 23 Brule St North side of Pinecrest Dr opposite REC New concrete pad and sidewalk Construction started September 2024
Pinecrest Dr At Civic 103 (7452) 103 Pinecrest Dr South side of Pinecrest Dr abutting Civic 103 New concrete pad and sidewalk Construction started September 2024
Pinecrest Dr At Civic 112 (2329) 112 Pinecrest Dr North side of Pinecrest Dr abutting Civic 112 New stop, concrete pad, and sidewalk Construction started September 2024
Pinecrest Dr At Civic 122 (7454) 122 Pinecrest Dr North side of Pinecrest Dr abutting Civic 122 Removal of stop, consolidation of Stops Pinecrest Dr At Civic 122 (7454) and Pinecrest Dr Before Civic 108 (7453), creation of new Stop Pinecrest Dr At Civic 112 (2329) with new concrete pad between curb and sidewalk Construction started September 2024
Pinecrest Dr At Civic 123 (7455) 123 Pinecrest Dr South side of Pinecrest Dr abutting Civic 123 New concrete pad and sidewalk Construction started September 2024
Pinecrest Dr Before Civic 108 (7453) 108 Pinecrest Dr North side of Pinecrest Dr abutting Civic 112 Removal of stop, consolidation of Stops Pinecrest Dr At Civic 122 (7454) and Pinecrest Dr Before Civic 108 (7453), creation of new Stop Pinecrest Dr At Civic 112 (2329) with new concrete pad between curb and sidewalk Construction started September 2024
Princess Margaret Blvd After Hudson Way (8070) 30 Iroquois Dr South side of Princess Margaret Blvd near Civic 30 New and extended concrete pad between curb and sidewalk Pending 2024 construction
Princess Margaret Blvd After Windmill Rd (8075) 463 Windmill Rd North side of Princess Margaret Blvd abutting 463 Windmill Rd New concrete pad and sidewalk Pending 2024 construction
Princess Margaret Blvd At Civic 40 (8071) 40 Princess Margaret Blvd West side of Princess Margaret Blvd adjacent Civic 40 New concrete pad Pending 2024 construction
Princess Margaret Blvd At Civic 55 (8072) 55 Princess Margaret Blvd West side of Princess Margaret Blvd adjacent Civic 55 New concrete pad Pending 2024 construction
Princess Margaret Blvd Before Hudson Way (8076) 465 Princess Margaret Blvd North side of Princess Margaret Blvd abutting Civic 465 New concrete pad and sidewalk to intersection Pending 2024 construction
Princess Margaret Blvd Before Windmill Rd (8078) 461 Windmill Rd South side of Princess Margaret Blvd abutting 461 Windmill Rd New concrete pad between curb and sidewalk Pending 2024 construction
Ronald Smith Ave After Ilsley Ave (8241) 121 Ilsley Ave South side of Ronald Smith Ave adjacent 121 Ilsley Ave New concrete pad between curb and sidewalk Completed July 2024
Windmill Rd After Akerley Blvd (8533) 743 Windmill Rd South side of Windmill Rd adjacent Civic 743 New concrete shelter pad and shelter Completed March 2024
Windmill Rd Before Dawn Dr (8522) 696 Windmill Rd North side of Windmill Rd abutting Civic 696 Shelter replacement Completed January 2024
Woodlawn Rd After Mt Edward Rd (8590) 54 Woodlawn Rd Northwest side of Woodlawn Rd abutting Civic 54 Slight relocation, new concrete pad between curb and sidewalk, removal of old concrete, reinstatement of sod Completed August 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bell Rd After Robie St (6291) 1840 Bell Rd South side of Bell Rd Slight relocation and pad extension Construction starting November 2024
Inglis St At SMU (6965) 5932 Inglis St South side of Inglis St near SMU Extension of pad and shelter pad Construction starting September 2024
Inglis St Before Robie St (2322) 5985 Inglis St North side of Inglis St near playground New concrete pad between the curb and the sidewalk, new stop Construction starting September 2024
Inglis St Before Robie St (6966) Inglis St Elementary School North side of Inglis St near the elementary school Consolidation of Stops Inglis St Before Robie St (6966) and Inglis St Opposite SMU (6960), relocation of stop at the location of work, removal of old stop and concrete pad Construction starting September 2024
Inglis St Opposite SMU (6960) 5915 Inglis St North side of Inglis St near Civic 5915 Consolidation of Stops Inglis St Before Robie St (6966) and Inglis St Opposite SMU (6960), relocation of stop at the location of work, removal of old stop and concrete pad Construction starting September 2024
Robie St Opposite Binney St (8219) 1600 Summer St East side of Robie Street near the cemetery Slight relocation, new concrete pad between curb and sidewalk Construction started July 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Duffus St After Novalea Dr (6583) 5521/5515 Duffus St North side of Duffus St abutting Civic 5521/5515 Shelter replacement Pending 2024 construction
Oxford St Before Berlin St (7405) 2733 and 2745 Oxford St East side of Oxford St in between Civics 2733 and 2745 New concrete pad between curb and sidewalk Pending 2024 construction
Quinpool Rd Before Windsor St (8261) 6067 Quinpool Rd North side of Quinpool Rd adjacent playground Installation of larger shelter Completed July 2024
Robie St Before Cabot St (8203) 3468 Robie St Southwest side of Robie St abutting Civic 3468 Shelter replacement Pending 2024 construction
Windsor St After Connaught Ave (8551) 3628 Windsor St South side of Windsor St abutting Civic 3628 Concrete pad extension Pending 2024 construction
Windsor St Before Maxwell Ave (8565) 3380 Windsor St South side of Windsor St abutting Civic 3380 Slight relocation, new concrete pad between curb and sidewalk Pending 2024 construction
Windsor St Opposite London St (8572) 2901 Windsor St Northeast side of Windsor St abutting Civic 2901 Shelter replacement Pending 2024 construction
Young St After Monaghan Dr (8629) 6141 Young St Northwest side of Young St abutting Civic 6141 Shelter replacement Pending 2024 construction
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Desmond Ave After Bayers Rd (6563) Opposite 3366 Desmond Ave East side of Desmond Ave before Stop Desmond Ave After Bayers Rd (6563) Extension of landing pad Pending 2024 construction
Herring Cove Rd Before Melwood Ave (6900) 1065 Purcells Cove Rd Southeast side of Herring Cove Rd south of Melwood Ave Shelter replacement Completed March 2024
Joseph Howe Dr After Scot St (2325) 3601 Joseph Howe Dr East side of Joseph Howe Dr near Superstore New concrete pad between the curb and sidewalk, new shelter pad and shelter behind the sidewalk Pending 2024 construction
Joseph Howe Dr Before Abbott Dr (6979) Opposite 7165 Abbott Dr West side of Joseph Howe Dr opposite 7165 Abbott Dr New shelter pad and shelter Pending 2024 construction
Joseph Howe Dr Before Dutch Village Rd (6984) 3627 Joseph Howe Dr East side of Joseph Howe Dr near Mobil Gas Station Removal of bus shelter and signage, relocation of the stop to 3601 Joseph Howe Dr Pending 2024 construction
Mumford Rd Opposite Hemlock St (7279) Opposite 7083 Mumford Rd South side of Mumford Rd abutting the cemetery Shelter replacement Completed March 2024
Purcells Cove Rd After Dingle Rd (8118) 1452 Purcells Cove Rd East side of Purcells Cove Rd abutting Civic 1452 Shelter replacement Pending 2024 construction
Purcells Cove Rd After Sailboat Ln (8122) Opposite 1255 Purcells Cove Rd North side of Purcells Cove Rd near Reserve Rd Shelter replacement Pending 2024 construction
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bedford Hwy After Torrington Dr (6279) 2 Torrington Dr South side of Bedford Hwy adjacent 2 Torrington Dr Shelter replacement Pending 2024 construction
Dutch Village Rd Before Andrew St (6609) 3543 Dutch Village Rd East side of Dutch Village Rd near Civic 3543 New concrete landing pad and sidewalk Pending 2024 construction
Dutch Village Rd Before Central Ave (6788) 3433 Dutch Village Rd North side of Dutch Village Rd near Civic 3433 New concrete landing pad and sidewalk Pending 2024 construction
Dutch Village Rd Before Rufus Ave (6614) 3600 Dutch Village Rd West side of Dutch Village Road near Civic 3600 New concrete landing pad and sidewalk Pending 2024 construction
Kearney Lake Rd After Hamshaw Dr (7021) 209 Kearney Lake Rd North of Kearney Lake Dr near Civic 209 Slight relocation with new bus pad Pending 2024 construction
Rosedale Ave After Alex St (8249) 63 Rosedale Ave North side of Rosedale Ave near Civic 61 Slight relocation with new bus pad Complete August 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Greystone Dr After Cobalt Walk (6798) 160 Lavender Walk At the cul-de-sac of Greystone Dr near Civic 160 New concrete pad between the curb and sidewalk Completed August 2024
Greystone Dr Opposite Cranberry Ct (6795) 147 Greystone Dr South side of Greystone Dr near Civic 147 New concrete pad between the curb and sidewalk Completed August 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Chain Lake Dr At Civic 209 (6394) 209 Chain Lake Dr West side of Chain Lake Dr abutting Civic 209 Concrete pad extension Construction starting September 2024
Julius Blvd Before Dugger McNeil Dr (2315) 125 Julius Blvd South side of Julius Blvd adjacent Civic 125 New concrete pad between curb and sidewalk Pending 2024 construction
Julius Blvd Before Dugger McNeil Dr (2317) 82 Julius Blvd North side of Julius Blvd adjacent Civic 85 New concrete pad between curb and multi-use path Pending 2024 construction
Maplewood Dr Before St Margarets Bay Rd (7180) 10 Maplewood Dr South side of Maplewood Dr after Beechville-Lakeside-Timberlea trailhead Slight relocation of stop, new concrete pad Construction starting September 2024
St Margarets Bay Rd After Clearwater Dr (6175) 1 Devonshire Dr North Side of St Margarets Bay Rd after Devonshire Dr and St Margarets Bay Rd intersection New concrete pad and pedestrian ramp to intersection Construction starting September 2024
St Margarets Bay Rd After Raines Mill Rd (2328) 2 Raines Mill Rd North side of St Margarets Bay Rd abutting 2 Raines Mill Rd Relocation of Stop St Margarets Bay Rd Before Raines Mill Rd (6180), new concrete pad between the curb and sidewalk Pending 2024 construction
St Margarets Bay Rd at civic 1917 (2330) 1917 St Margarets Bay Rd North side of St Margarets Bay Rd abutting Civic 1917 Relocation of Stop St Margarets Bay Rd At Civic 1939 (6149) at the location of work, new concrete pad between the curb and sidewalk Pending 2024 construction
St Margarets Bay Rd At Civic 1922 (6170) 1928 St Margarets Bay Rd South side of St Margarets Bay Rd near Civic 1928 New concrete pad between curb and sidewalk Pending 2024 construction
St Margarets Bay Rd At Civic 1939 (6149) 1939 St Margarets Bay Rd North side of St Margarets Bay Rd near Civic 1917 Relocation of stop to further east side of St Margarets Bay Rd, new concrete pad Pending 2024 construction
St Margarets Bay Rd Before Raines Mill Rd (6180) 1403 Lakeside Dr North side of St Margarets Bay Rd near Civic 1403 Lakeside Dr Relocation of stop at the location of work, installation of new bus pad adjacent to sidewalk Pending 2024 construction
St Margarets Bay Rd Before Sheppards Run (6157) 438 Sheppards Run South side of St Margarets Bay Rd adjacent 438 Sheppards Run Shelter replacement March 2024 construction
St Margarets Bay Rd Opposite Boylan Ln (6164) 1370 St Margarets Bay Rd South side of St Margarets Bay Rd abutting Civic 1370 New concrete bus pad and sidewalk from Raines Mill Rd to Oliver St, connecting shelter pad to an accessible pedestrian route Pending 2024 construction
Susie Lake Cr Before Julius Blvd (2313) 420 Susie Lake Cr North side of Susie Lake Cr opposite Civic 420 New concrete pad between curb and sidewalk, new concrete shelter pad, and new shelter Completed March 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Beaver Bank Rd After Welkin Dr (8755) 352 Beaver Bank Rd West side of Beaver Bank Rd opposite Civic 345 New signpost, concrete pad, and sidewalk connection to intersection at Welkin Dr Completed 2024
Beaver Bank Rd Before Welkin Dr (8713) 343 Beaver Bank Rd East side of Beaver Bank Rd near Civic 343 Relocation bus stop forward ~10m, concrete pad increase, installation of signpost Completed May 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Cobequid Rd After Freer Ln (6434) 191 Cobequid Rd East side of Cobequid Rd near Civic 191 New shelter pad Pending 2024 construction
Cobequid Rd After Maple Grove Dr (6431) 450 Cobequid Rd West side of Cobequid Rd near Civic 450 New shelter pad Pending 2024 construction
Cobequid Rd Before Maple Grove Dr (6441) 473 Cobequid Rd East side of Cobequid Rd near Civic 477 Slight relocation to Civic 477, new concrete pad between curb and sidewalk Pending 2024 construction
First Lake Dr After Civic 192 (6683) 192 First Lake Dr North side of First Lake Dr near Civic 192 New sidewalk connection to concrete pad Completed July 2024
Sackville Dr Before Armoyan Dr (7313) 300 Sackville Dr West side of Sackville Dr abutting Civic 300 Shelter replacement Pending 2024 construction
Sackville Terminal Bay 4 (8960) Sackville Terminal Sackville Terminal Shelter replacement Pending 2024 construction
Stokil Dr After Grennan Dr (8354) 86 Grennan Dr West side of Stokil Dr near 86 Grennan Dr Concrete pad replacement Completed September 2024
Stokil Dr After Grennan Dr (8356) 253 Stokil Dr East side of Stokil Dr near 1 Armcrest Dr Slight relocation to 1 Armcrest Dr, new concrete pad between curb and sidewalk Completed September 2024
Stokil Dr After Sampson Dr (8355) 2 Sampson Dr North side of Stokil Dr near 2 Sampson Dr Concrete pad replacement Completed September 2024
Stokil Dr Before Smokey Dr (8358) 241 Smokey Dr West side of Stokil Dr adjacent the elementary school Concrete pad replacement Completed September 2024
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bus Stop Location Nearest Civic Address Location of Work Scope of Work Status
Bedford Hwy After Charlotte Ln (6287) 587 Bedford Hwy East side of Bedford Hwy near Civic 587 New concrete pad with sidewalk connection and shelter with shelter pad Pending 2024 construction
Bedford Hwy After Shaunslieve Dr (6234) 34 Shaunslieve Dr West side of Bedford Hwy near Civic 34 New concrete pad and shelter, removal of old shelter pad Pending 2024 construction
Bedford Hwy Before Spring St (6249) 1326 Bedford Hwy Northwest side of Bedford Hwy abutting Civic 1326 Shelter replacement Pending 2024 construction
Bedford Hwy Before Union St (6228) 1488 Bedford Hwy North side of Bedford Hwy abutting Civic 1488 Shelter replacement Completed January 2024
Broad St Before Larry Uteck Blvd (2027) 51 Jam Ln North side of Broad St adjacent 51 Jam Ln New concrete shelter pad and shelter Construction starting November 2024
Larry Uteck Blvd After Kearney Lake Rd (6298) 1000 Larry Uteck Blvd South side of Larry Uteck Blvd abutting Civic 1000 New concrete pad, shelter, sidewalk connection, and RA-5 crosswalk Completed January 2024
Larry Uteck Blvd Before Abbington Ave (7022) 29 Abbington Ave Northeast side of Larry Uteck Blvd adjacent Civic 29 New bus pad, sidewalk connection, and RA-5 crosswalk Completed August 2024
Larry Uteck Blvd Before Belle St (7027) 3 Belle St Southwest side of Larry Uteck Blvd adjacent 3 Belle St New bus pad, sidewalk connection, and RA-5 crosswalk Completed August 2024